Project Description

2009
Installation of new filters REDECAM Italy on the cement silos 1-4, cement mills #2&8 and kiln #2

  • Installation of switching cabinets and installation of uninterruptible power systems in the server room
  • Installation of control cabinets in the switchboard room
  • Installation of cable trays, local boxes and equipment by Redecam and Siemens
  • Laying and connection of power, control and optical fiber cables
  • Testing of cables
  • Commissioning

Project Details