Industrias Alegre (Biskupice Podgorne, Poland)

July – December 2016

Transfer current transformers (2MhVt) – 7 pcs. from Industrial Space for transformer substation.

Read More
1

Cement Factory in Kryviy Rih (PJSC “HeidelbergCement Ukraine”)

February – March 2015
Installation works on the project: ” Installation works on the project: “Automated system for unloading wagons” to PJSC “Heidelb

Read More
header_bg

“CASPIICEMENT” LLP (PJSC “HeidelbergCement Kazakhstan”, Shetpe, Republic of Kazakhstan)

June – September 2014
A range of “turnkey” to “desalination stations’ under the following headings:

power supply
technology
lighting
electric heating

Read More
header_bg

PJSC “VOLYN CEMENT” («Dyckerhoff Ukraine»)

November 2013-February 2014
Electrical work on the modernization of the kiln # 4 and the refrigerator #4

Installation of cable structures (PUK WERKE system) in the cooler areas, a

Read More
img_3013

GÓRAŻDŻE CEMENT S.A. (Poland)

November 2010 – April 2011
Electrical work on the modernization of kiln #2, the kiln’s refrigerator #2, and coal section

Removal of old cable lines and cable products

Read More
1

Cement Factory in Kryviy Rih (PJSC “HeidelbergCement Ukraine”)

August – December 2010
Electricinstallationworkson commissioning electrical and control installationfor coal millforOJSC HeildelbergCement Ukraine in Kryvyi Rih

raw coal storage

Read More
21

Cement Factory «Doncement» affiliate Amvrosiyevka (cement plant placed in Donetsk region)

January – June 2010
Electricinstallationworkson commissioning electrical and control installationfor coal millforPSJ HeildelbergCement Ukraine affiliate Amvrosiyevka(cement plan

Read More
b6

JSC “Bukhtarma Cement Company” (PJSC “HeidelbergCement Kazakhstan”, Bukhtarma, Republic of Kazakhstan)

2010
Installation of new filters REDECAM Italy on the cement mill # 6&7 and kiln #1

Installation of switching cabinets and installation of uninterruptible power systems in th

Read More
b6

JSC “Bukhtarma Cement Company” (PJSC “HeidelbergCement Kazakhstan”, Bukhtarma, Republic of Kazakhstan)

2009
Installation of new filters REDECAM Italy on the cement silos 1-4, cement mills #2&8 and kiln #2

Installation of switching cabinets and installation of uninterruptible po

Read More
header_bg

PJSC “VOLYN CEMENT” («Dyckerhoff Ukraine»)

August – October 2014
Electrical work on the modernization of farms crane linear materials warehouse

Installation of cable structures (PUK WERKE system) indoor substations a

Read More